At leading CEE refinery – SLOVNAFT Bratislava, we undertook the distinctive task of replacing the F1 furnace within Atmospheric Distillation Unit 5. The new furnace was skilfully assembled on-site from prefabricated components, well in advance of the unit’s general overhaul.

Upon decommissioning, the legacy furnace was meticulously segmented into four sections using a water disc. Using a formidable 750-ton belt crane, the newly crafted furnace was then precisely positioned onto the original base and seamlessly integrated with the existing infrastructure.

This project exemplifies our commitment to cutting-edge solutions, precision, and seamless execution.

Details

HOURS INVESTED:
Preliminary Work: Approximately 17,400 hours
Shutdown Operations: Roughly 25,245 hours

WORKFORCE ENGAGEMENT
At the zenith of the project, we had between 40 to 50 dedicated professionals working daily during the shutdown period. 

 

SHUTDOWN DURATION
51 productive days

Safety Record: Proudly, the entire project was executed without any injuries or HSE incidents. Safety and well-being remain at the forefront of our operations.